solarpanelsforagriculture

How much do solar panels for agriculture cost?

Indicative UK costs by system size, sub-vertical, and financing route. Updated for 2026.

The honest answer to "what does farm solar cost" is that it depends almost entirely on what kind of farm you are. A 30 kW dairy parlour install and a 5 MW ground-mount scheme on marginal pasture are both "farm solar", and they sit at opposite ends of a very wide range. What follows is an indicative picture of typical agricultural solar costs across the UK, to help you sense-check the quotes you receive.

Cost per kW: the headline figures

For rooftop installs, the cost per kilowatt falls as the system gets bigger, because the fixed costs of scaffolding, design, grid application and commissioning are spread across more panels. The only official series is from DESNZ (May 2026): MCS-registered installs of 10 to 50 kW had a median cost of £1,204 per kW (VAT where applicable). Above 50 kW there is no official series, so these figures are indicative, from installer and industry price guides: roughly £750 to £1,050 per kW at 100 kW, £700 to £950 at 250 kW and £650 to £900 at 500 kW, ex VAT. Large ground-mount is cheaper per kW again, because the racking is simpler and there is no roof to work around: Arup's study for DESNZ (July 2025, 2023 prices) put arrays of 5 MW and above at £526 to £789 per kWp excluding land, and smaller farm ground-mounts cost more per kW.

To put that in money: a 100 kW system to suit a mid-sized dairy or livestock unit lands somewhere around £75,000 to £105,000 ex VAT before tax relief. A 250 kW array on a large poultry shed or arable grain store sits closer to £175,000 to £240,000. Both exclude grid reinforcement, re-roofing and batteries. A megawatt-scale ground-mount scheme runs into the hundreds of thousands or millions, though those are usually delivered under a developer-lease model where the farm does not carry the capital cost at all.

What you actually pay by farm type

Dairy farms are the clearest case when the array is sized to the daytime load: around-the-clock milk cooling and parlour load mean most of the output can be used on site, giving an indicative payback of roughly four to seven years at 24p to 28p avoided import. Size it to annual consumption instead and far more is exported: an Irish Teagasc model (July 2025) of a 100-cow farm found 27% of output used on site (41% with a battery). Arable farms are more variable: the big grain-drying load is seasonal, so the question is whether to size for that autumn peak and export the rest, or build a smaller system and add battery storage. Livestock units with large clear-span sheds and high ventilation loads, broiler and layer poultry especially, behave a lot like dairy, with high self-consumption and good payback. Horticulture and glasshouse sites, with their heavy lighting and pump loads, sit at the fast-payback end too. The cards lower down this page give the indicative figures for each.

How farms pay for it

There are three main routes, and they suit different farms. The first is a cash purchase paired with capital allowances. Most farm installs fall well within the £1m Annual Investment Allowance, which means a limited-company farm can write off the full cost of qualifying solar plant against tax in the year it is installed, an effective saving of up to 25% for companies at current corporation tax rates, with comparable relief for sole-trader and partnership farms. You can read more about the rules on the government's capital allowances guidance. For a farm with the cash and a tax bill to offset, this is usually the lowest-cost route over the life of the system.

The second route is asset finance, where the system is paid off over five to ten years. Done well, the energy saving is larger than the monthly finance payment from early on, so the install is broadly cash-flow positive without tying up the farm's own capital. The third route is a power purchase agreement or land lease, where a third party funds and owns the array and the farm either buys the power at a discount or takes a rent for the land. Ground-mount lease income on marginal land typically runs about £800 to £1,000 per acre per year (Arup developer survey for DESNZ, July 2025; land agents quoted £850 to £1,100 in 2023-24), well above arable rental value, and the developer carries all the capital and operational risk.

Measuring the return: payback, IRR and the export question

Simple payback, the number of years for savings to repay the capital, is the figure most farmers ask for first, and it is a fair starting point. But it ignores everything after the system has paid for itself, and a good farm array runs for 25 years or more. Internal rate of return and net present value give a fuller picture of lifetime value, and it is worth asking the installer to show all three in any proposal. The single biggest variable is self-consumption: every unit you use on site is worth the grid price you avoid (DESNZ puts the average non-domestic price at 28.6p per kWh for sites using 20 to 499 MWh a year, Q2 2026, incl. CCL, ex VAT), while every unit exported earns the Smart Export Guarantee tariff, roughly 3p to 15p per kWh for business tariffs depending on supplier. That is why sizing the system to your real load matters so much, and why a good installer should start from your half-hourly meter data rather than a rule of thumb.

The costs people forget

A few items sit outside the headline panel-and-inverter price, and being upfront about them avoids unwelcome surprises. Grid connection is the main one: anything above 16 A per phase (3.68 kW single-phase, about 11 kW three-phase) needs a G99 application to the network operator, and on capacity-constrained rural feeders that can mean both a connection charge and a wait of several months to well over a year. Where export capacity is tight, a no-export design sized for self-consumption can avoid much of this cost and delay. Structural survey and any roof strengthening, scaffolding or access equipment, and the cost of an upgraded incoming supply or new switchgear can all feature depending on the site.

The big one specific to farms is roofing. Many farm buildings from before 2000 carry asbestos cement sheeting, which should not take panels and needs removing first; most asbestos-cement sheet removal is non-licensed work but must be done by trained, competent contractors following HSE guidance. The usual approach is a combined strip-and-reclad to profiled steel followed by PV on the new roof. It adds cost, but the solar business case often helps fund a re-roof the farm needed anyway, so it is worth treating as one project rather than two.

Timeline and cash flow

From first conversation to commissioning, a rooftop farm install typically takes four to nine months, with the grid connection usually the longest single item. The physical install itself is short, a week or two for most rooftop systems, and you can ask the installer to schedule it around your busy seasons so it does not clash with calving, lambing or harvest. Once the system is live, the savings start immediately, and for a daytime-load farm on asset finance the install can be cash-flow positive from the first or second month. Set against DESNZ non-domestic electricity prices of 27.7p to 38.4p per kWh in Q2 2026 for businesses using under 2,000 MWh a year (incl. CCL, ex VAT, depending on consumption band), the case for farm solar turns on how much of the output you use on site.

Cost ranges by sub-vertical

Dairy Farms

Typical system
30-250 kW
Project value
£30,000-£240,000
Payback
4-10 years (indicative)
Annual generation
24,000-250,000 kWh

Arable Farms

Typical system
30-500 kW (rooftop) + ground mount potential to 5+ MW
Project value
£30,000-£450,000 (rooftop)
Payback
6-13 years (indicative, seasonal load)
Annual generation
24,000-500,000 kWh

Livestock Farms (Beef/Sheep/Pig/Poultry)

Typical system
20-300 kW
Project value
£20,000-£285,000
Payback
4-13 years (indicative)
Annual generation
16,000-300,000 kWh

Glasshouse / Horticulture

Typical system
100 kW-5 MW
Project value
£75,000-£4m
Payback
4-10 years (indicative)
Annual generation
80,000-5m kWh

Agrivoltaic / Mixed Use

Typical system
500 kW-10+ MW
Project value
£325,000-£8m (ex land)
Payback
Varies; often a land lease
Annual generation
varies kWh

Equestrian Centres & Stables

Typical system
20-150 kW
Project value
£20,000-£160,000
Payback
6-13 years (indicative)
Annual generation
16,000-150,000 kWh

Cost questions

How much do solar panels for a farm cost in the UK?

Dairy and livestock parlour installs (30-250 kW): roughly £30,000-£240,000, ex VAT (indicative). Arable rooftop installs (50-500 kW): roughly £45,000-£450,000. The official DESNZ median (May 2026) for 10-50 kW installs is £1,204 per kW; above 50 kW there is no official series, and indicative industry guide prices run about £750-£1,050 per kW at 100 kW and £650-£900 per kW at 500 kW, ex VAT, excluding grid reinforcement, re-roofing and batteries. Utility ground-mount of 5 MW and above costs about £526-£789 per kWp excluding land (Arup for DESNZ, July 2025, 2023 prices).

What's the payback for a dairy farm solar install?

Indicative only: roughly 4-7 years if sized to the daytime load. Self-consumption depends on sizing: an array sized to the daytime load (milk cooling, parlour pumps) uses most of its output on site, while one sized to annual consumption exports much more. An Irish Teagasc model (July 2025) of a 100-cow farm with an array sized to annual use consumed 27% on site (41% with a battery). The band assumes 24-28p avoided import and 3-5p export; the 100% AIA shortens the post-tax payback.

Get a quote to compare with these costs

  • 1. Tell us about the holding — buildings, land and rough annual electricity spend.
  • 2. We pass your enquiry on to an installer covering your area. No obligation.
  • 3. Check before you sign — look the installer up on the MCS and RECC registers and compare any quote with our cost guide.

By submitting you agree to our privacy policy. We pass your details to an installer covering your area so they can reply to this enquiry.

Get a free quote
Get a free quote